top of page

2807 Getting the "Life of Riley!"



Cotswold Steam Preservation Ltd (CSPL) are pleased to announce that, after a particularly challenging period for everyone due to COVID lockdowns, via Zoom meetings and many emails, the scope of work to overhaul the Boiler of 2807 has been agreed with Ian Riley’s Engineering Ltd (Riley’s). This is a huge milestone and will now allow CSPL and Riley’s to move forward and focus on the specific work required to complete the boiler overhaul.


2807's boiler arrives at Riley's


The high-level scope of work has been defined as follows: Replace the front boiler barrel section and smoke box tube plate for new Replace the back head from just below the fire hole door down to the foundation ring Repairs to the foundation ring Work to replace sections of the smoke box and smoke box door plate Complete set of new tubes Various other items to facilitate the above


Front tube plate removal

Brian Gamlin the CSPL Chairman commented: With not being able to visit Ian and his team the process has taken longer than expected, this has been frustrating for all. We are incredibly pleased to have got to this point and reaffirm that we made the correct decision to award this work to Riley’s. My thanks go to Ian, Greg, and Andy from Riley’s and to Gilbert Kitchen the CME for CSPL for their hard work so far” Comments from The Team at Riley’s: Riley's are delighted that CSPL chose to trust us with the boiler work for 2807. The Pandemic has meant that no face-to-face meetings around the boiler have been possible. But CSPL and Riley's have worked together to overcome this, and we are very pleased to have agreed a scope of works and to have the positive support of CSPL that will enable us to start work immediately.”


2807's smoke box removed

CSPL are planning to restart the HGO on the 31st March and will work closely with the Gloucestershire Warwickshire Steam Railway (GWSR) over the coming months to get back to an “almost” normal pattern of working. Before lock down the major strip down of the main loco frames was completed. We still have a few little things to do but we can now focus on, and see, the major milestone of putting things back together. We have a long way to go and have been impacted by COVID but the CSPL team are an amazing group of volunteers that will work extremely hard to get 2807 back into steam as soon as possible. CSPL have added that with the HMG lockdown exit plan they are looking to restart the HGO on the 31st March as planned. The HGO team are starting to organise working parties (rule of 6) from the 31st March and CSPL will work with the GWSR as things move forward over the next few months. Watch this space for updates on the wheels sets, currently at South Devon Railway for tyre and journal re-profiling. Also for a pending announcement re the boiler work to be carried out at Ian Riley's Engineering.


2807 at the North Yorkshire Moors Railway in September 2014

9 views0 comments
bottom of page